EL24-015 - In the Matter of the Application by Otter Tail Power Company and Western Minnesota Municipal Power Agency for a Facility Permit for a 345-kV Transmission Facility and Associated Facilities in Grant County, South Dakota
Pre-filed Testimony and Exhibits
Applicant – Otter Tail Power Company and Western Minnesota Municipal Power Agency Pre-filed Testimony
- 04/15/24 – Pre-filed Direct Testimony
- 10/25/24 - Otter Tail Power Company and Western Minnesota Municipal Power Agency's Letter Regarding Supplemental Testimony and Certificate of Service
- Pre-Filed Supplemental Direct Testimony of Jason Weiers
- Exhibit A - Summary of Route Adjustments
- Exhibit B - Updated Application Appendix A (Figures)
- Figure A1 - Project Location
- Figure A2 - BSSA Project Location
- Figure A3 - Public Outreach Study Area
- Figure A4a - Detailed Project Layout
- Figure A4b - Detailed Project Layout
- Figure A4c - Detailed Project Layout
- Figure A4d - Detailed Project Layout
- Figure A4e - Detailed Project Layout
- Figure A4f - Detailed Project Layout
- Figure A5 - Big Stone South Substation Layout
- Figure A6 - Parcels within 0.5-mile of the Flexibility Area
- Figure A7 - Topography
- Figure A8 - Bedrock Geology
- Figure A9 - Surficial Geology
- Figure A10 - Bedrock Geology Cross Section
- Figure A11 - Surficial Geology Cross Section
- Figure A12 - Land Use
- Figure A13 - Soil Types
- Figure A14 - Surface Water and Wetland Resources
- Figure A15 - Land Cover
- Figure A16 - Public Lands and Facilities
- Exhibit C - Additional Landowner Notice Documentation
- Exhibit C-1 - Additional Landowner Mailing List Confidential (not available to the public)
- Exhibit D - Xcel Energy Affidavit
- Exhibit E - Grant County Conditional Use Permit Letter of Assurance
- Pre-Filed Supplemental Direct Testimony of Kevin Scheidecker
- Exhibit A - Supplemental Level I Cultural Resource Letter Report Dated August 20, 2024, Confidential (not available to the public)
- Pre-Filed Supplemental Direct Testimony of Jason Weiers