EL22-031 - In the Matter of the Petition of Otter Tail Power Company for
Approval of the Transmission Cost Recovery Rider Rate
Date Filed: 11/01/22 ♦ Intervention Date: 11/18/22
Date of Notice of Filing: 11/03/22 ♦ Docket Closed: 02/17/23
Date of Notice of Filing: 11/03/22 ♦ Docket Closed: 02/17/23
Agendas:
February 9, 2023, Agenda of Commission Meeting
Minutes:
Minutes of the February 9, 2023 Commission Meeting
- 11/01/22 - Otter Tail Power Company's Letter regarding Petition
- Request for Confidential Treatment of Information
- Petition for Annual Update to Transmission Cost Recovery Rider Rate
- Petition for Annual Update to Transmission Cost Recovery Rider Rate Excerpt Confidential (not available to the public)
- Attachment List
- Attachment 1 - Projected Revenue
- Attachment 2 - Revenue Requirements Summary
- Attachment 3 - Rate Design
- Attachment 4 - Tracker Summary
- Attachment 5 - Lake Norden Area Revenue Requirements Calculation
- Attachment 6 - Big Stone South to Ellendale MVP Revenue Requirements Calculation
- Attachment 7 - Erie Project
- Attachment 8 - Norcross Project
- Attachment 9 - Oslo 115 kV Breaker Station and Oslo – Lake Ardoch 115 kV Line
- Attachment 10 - Transmission Adjustment EL18-021
- Attachment 11 - Attachment O Revenue Credit Calculation for Non-MISO Projects
- Attachment 12 - MISO Schedule 26 and 26A Expense
- Attachment 13 - SPP Schedule 9 and 11 Expenses
- Attachment 14 - MISO Schedule 9 Revenue
- Attachment 15 - MISO Schedule 26 Revenue
- Attachment 16 - MISO Schedule 26A Revenue
- Attachment 17 - MISO Schedule 37 and 38 Revenue
- Attachment 18 - MISO Multi-Value Project Auction Revenue Rights Credit
- Attachment 19 - ADIT Pro-Rate Projection
- Attachment 20 - ADIT Pro-Rate Preservation
- 02/06/23 - Staff Memorandum
- 02/17/23 - Otter Tail Power Company's Letter regarding Tariff Page and Response to Commissioner’s Question
- 02/17/23 - Docket Closed
- 05/30/23 - Otter Tail Power Company’s Letter regarding 2022 Annual Report