EL12-054 - In the Matter of the Petition of Otter Tail Power Company for Approval of its 2013 Transmission Cost Recovery Eligibility and Rate Adjustment
Date Filed: 09/04/12 ♦ Intervention Date: 09/21/12 ♦ Docket Closed: 04/25/13
Docket Reopened: 05/21/14 ♦ Docket Reclosed: 06/02/14
Weekly Filing:
Weekly Filing 08/30/12 to 09/05/12
Agendas:
May 27, 2014, Addendum to Agenda of Commission Meeting
April 23, 2013, Agenda of Commission Meeting
September 25, 2012, Agenda to Commission Meeting
Minutes:
Minutes of May 27, 2014, Commission Meeting
Minutes of April 23, 2013, Commission Meeting
Minutes of September 25, 2012, Commission Meeting
- Order Assessing Filing Fee and Suspending Operation of Rate Schedule
- Order Granting Joint Motion for Approval of Settlement Stipulation
- Order Approving Request for Extension of Time to File TCR Annual Report
- 09/04/12 - Otter Tail Power's Letter regarding
its 2013 Transmission Cost Recovery Eligibility and Rate Adjustment
- Petition for Annual Update to Transmission Cost Recovery Rider Rate
- Attachment List
- Attachment 1 - Projected Revenue for 2013
- Attachment 2 - Revenue Requirements Summary
- Attachment 3 - Class Allocation and Rate Design
- Attachment 4 - Tracker Summary
- Attachment 5 - CAPX Fargo-Monticello Revenue Requirements Calculation
- Attachment 6 - CAPX Bemidji-Grand Rapids Revenue Requirements Calculation
- Attachment 7 - Rugby Wind Interconnection Revenue Requirements Calculation
- Attachment 8 - Casselton-Buffalo 115kV Project Revenue Requirements Calculation
- Attachment 9 - CAPX Brookings, SD-Hampton, MN Revenue Requirements Calculation
- Attachment 10 - MVP BSAT to BSS Brookings Revenue Requirements Calculation
- Attachment 11 - MVP Big Stone South to Ellendale Revenue Requirements Calculation
- Attachment 12 - Ramsey 230/115 KW Transformer Upgrade (Project #104766) Revenue Requirements Calculation
- Attachment 13 - Sheyenne-Audubon Upgrade (Project #104765 & #104818) Revenue Requirements Calculation
- Attachment 14 - Karlstad, MN Capacitor Bank Project Revenue Requirements Calculation
- Attachment 15 - Oakes Area Transmission Improvements (Project #104762) Revenue Requirements Calculation
- Attachment 16 - Hankinson Transformer Addition Revenue Requirements Calculation
- Attachment 17 - Attachment O Revenue Credit Calculation for Non-MISO Projects
- Attachment 18 - MISO Schedule 26 and 26A Expense
- Attachment 19 - MISO Schedule 26 Revenue
- Attachment 20 - MISO Schedule 26A Revenue
- Attachment 21 - MISO Schedule 37 and 38 Revenue
- Attachment 22 - Electric Rate Schedule Section 13.07 Redline and Clean
- Attachment 23 - Proposed Customer Notice and Rate Impact
- Attachment 24 - ARSD 20:10:13:26 Report to Commission of Tariff Schedule Changes on Notice
- Petition for Annual Update to Transmission Cost Recovery Rider Rate
- 09/18/12 - PUC Staff's Letter regarding Suspension of Rates, Regulatory Assessment Fee and Consultant Contracting Authority
- 04/17/13 - PUC Staff's Letter regarding Settlement Stipulation
- Joint Motion for Approval of Settlement Stipulation
- Settlement Stipulation
- Attachment 1 - Projected Revenue 2013
- Attachment 2 - Summary of Revenue Requirements
- Attachment 3 - Class Allocation and Rate Design
- Attachment 4 - Tracker Summary Requirements Compared to Billed
- Attachment 5 - CAPX2020 Fargo-Monticello Revenue Requirements
- Attachment 5 - CAPX2020 Fargo-Monticello Revenue Requirements Confidential (not available to the public)
- Attachment 6 - Bemidji-Grand Rapids Revenue Requirements
- Attachment 6 - Bemidji-Grand Rapids Revenue Requirements Confidential (not available to the public)
- Attachment 7 - Cass Lake - Bemidji Revenue Requirements
- Attachment 7 - Cass Lake - Bemidji Revenue Requirements Confidential (not available to the public)
- Attachment 8 - Rugby Wind Interconnection Revenue Requirements
- Attachment 8 - Rugby Wind Interconnection Revenue Requirements Confidential (not available to the public)
- Attachment 9 - Casselton – Buffalo 115 kV Revenue Requirements
- Attachment 9 - Casselton – Buffalo 115 kV Revenue Requirements Confidential (not available to the public)
- Attachment 10 - Schedule 26 & Schedule 26A Expense
- Attachment 11 - Schedule 26 Revenues
- Attachment 12 - Schedule 37 & Schedule 38 Revenues
- Attachment 13 - Revised Tariff Sheet
- Attachment 14 - Notice to Otter Tail Power Company Customers
- Staff Memorandum
- Staff Memorandum Confidential (not available to the public)
- Certificate of Service
- 04/25/13 - Docket Closed
- 05/31/13 - Otter Tail Power's Letter regarding Annual Report for Jurisdictional Earnings
- Request for Confidential Treatment of Information
- Annual Report of Jurisdictional Earnings
- Exhibit 1 - Return on Equity
- Exhibit 2 - Operating Income
- Exhibit 3 - Average Rate Base
- Exhibit 4 - Cost of Capital
- Exhibit 5 - Required Rate of Return - Public
- Exhibit 5 - Required Rate of Return Confidential (not available to the public)
- Exhibit 6 - Revenue Deficiency
- Public
- Exhibit 6 - Revenue Deficiency Confidential (not available to the public)
- 05/21/14 - Otter Tail's Letter regarding a 30 Day Extension Request for Annual Report Compliance Filing
- 06/02/14 - Docket Reclosed
- 06/27/14 - Otter Tail's Letter regarding Annual Report of Jurisdictional Earnings
- Request for Confidential Treatment of Information
- Annual Report of Jurisdictional Earnings
- Exhibit 1 - Return on Equity
- Exhibit 2 - Operating Income
- Exhibit 3 - Average Rate Base
- Exhibit 4 - Cost of Capital
- Exhibit 5 - Required Rate of Return
- Exhibit 5 Confidential (not available to the public)
- Exhibit 6 - Revenue Deficiency
- Exhibit 6 Confidential (not available to the public)
- Addendum 1 - Rate Base Summary
- Addendum 2 - Income Statement Summary
- Addendum 3 - Current Income Tax Summary
- Addendum 4 - Revenue Requirement & Return Summary
- Addendum 4 Confidential (not available to the public)