South Dakota Public Utilities Commission Meeting
May 27, 2014, at 1:30 P.M. CDT
Room 413, Capitol Building
Pierre, South Dakota
NOTE: If you wish to join this meeting by conference call, please contact the Commission at 605-773-3201 by 9:00 a.m. CDT on Tuesday, May 27, 2014. Lines are limited and are given out on a first come, first served basis, subject to possible reassignment to accommodate persons who must appear in a proceeding. Ultimately, if you wish to participate in the Commission Meeting and a line is not available, you may have to appear in person.
NOTE: To listen to the Commission Meeting live please go to the PUC's website www.puc.sd.gov and click on the LIVE link on the home page. The Commission requests persons who will only be listening to proceedings and not actively appearing in a case listen via the web cast to free phone lines for those who have to appear. The Commission meetings are archived on the PUC's website under the Commission Actions tab, Click on "Commission Meeting Archives," to access the recordings.
NOTE: Notice is further given to persons with disabilities that this Commission meeting is being held in a physically accessible place. If you have special needs, please notify the Commission and we will make all necessary arrangements.
ADDENDUM TO THE
AGENDA OF COMMISSION MEETING
Electric
On September 4, 2012, the Commission received a Petition from Otter Tail Power Company (Otter Tail) requesting approval of its annual update to its Transmission Cost Recovery Rider (TCR) rate. On April 24, 2013, the Commission issued an Order Granting Joint Motion for Approval of Settlement Stipulation. The Settlement Stipulation requires Otter Tail to make a compliance filing by June 1 of each year with a report of its South Dakota jurisdictional earnings for the preceding calendar year. On May 21, 2014, Otter Tail filed a letter requesting a 30 day extension to file the annual report by July 1, 2014.
TODAY, shall the Commission approve Otter Tail's request for an extension to July 1, 2014, to file the 2013 annual report of jurisdictional earnings?
On August 30, 2013, the Commission received a Petition from Otter Tail Power Company (Otter Tail) requesting approval of its annual update to its Transmission Cost Recovery Rider (TCR) rate. On February 21, 2014, the Commission issued an Order Granting Joint Motion for Approval of Settlement Stipulation. The Settlement Stipulation requires Otter Tail to make a compliance filing by June 1 of each year with a report of its South Dakota jurisdictional earnings for the preceding calendar year. On May 21, 2014, Otter Tail filed a letter requesting a 30 day extension to file the annual report by July 1, 2014.
TODAY, shall the Commission approve Otter Tail's request for an extension to July 1, 2014, to file the 2013 annual report of jurisdictional earnings?
/s/Cindy Kemnitz
Cindy Kemnitz
Finance Manager
PUC Email
May 20, 2014