EL18-026 - In the Matter of the Application by Prevailing Wind Park, LLC for a Permit of a Wind Energy Facility in Bon Homme County, Charles Mix County and Hutchinson County, South Dakota, for the Prevailing Wind Park Project
Date of Notice of Filing: 05/31/18 ♦ Docket Closed: 05/16/19
Docket Reopened: 06/13/19 ♦ Docket Reclosed: 11/09/23
Also see 04CIV18-000084
Agendas:
June 12, 2018, Agenda of Commission Meeting
August 7, 2018, Agenda of Commission Meeting
September 18, 2018, Agenda of Commission Meeting
September 21, 2018, Agenda of Ad Hoc Commission Meeting
October 31, 2018, Agenda of Commission Meeting
November 20, 2018, Ad Hoc Agenda of Commission Meeting
February 15, 2019, Agenda of Commission Meeting
May 14, 2019, Agenda of Commission Meeting
April 29, 2020, Agenda of the Commission Meeting
July 8, 2020, Agenda of Commission Meeting
Minutes:
Minutes of June 12, 2018, Commission Meeting
Minutes of August 7, 2018, Commission Meeting
Contact Precision Reporting to order a written transcript of EL18-026 discussion
Minutes of September 18, 2018, Commission Meeting
Contact Precision Reporting to order a written transcript of EL18-026 discussion
Minutes of September 21, 2018, Ad Hoc Commission Meeting
Contact Precision Reporting to order a written transcript of EL18-026 discussion
Minutes of October 31, 2018 Commission Meeting
Contact Precision Reporting to order a written transcript of EL18-026 discussion
Minutes of November 20, 2018 Ad Hoc Commission Meeting
Contact Precision Reporting to order a written transcript of EL18-026 discussion
Minutes of February 15, 2019 Commission Meeting
Minutes of May 14, 2019 Commission Meeting
Minutes of April 29, 2020, Commission Meeting
Minutes of July 8, 2020, Commission Meeting
Click For Comments and Responses
Pre-filed Exhibits and Witness Lists for Evidentiary Hearing
Hearing:Public Input Hearing on the Application on July 12, 2018, at 5:30 p.m., CDT, at the Avon School, 210 Pine St., Avon, S.D.
- 06/01/18 - Notice of Application; Order for and Notice of Public Input Hearing; Notice of Opportunity to Apply for Party Status
- South Dakota Public Utilities Commission Information Guide to Siting Energy Conversion & Electric Transmission Facilities
- Party Status Application
- Recording
- Prevailing Wind Park, LLC's Presentation
- Sign In Sheets
- Comments of Lori Fuerniss
- Comments of Lori Fuerniss Confidential (not available to the public)
- Comments of Ed Van Gerpen
- Comments of George L. Holborn
- Comments of George L. Holborn Confidential (not available to the public)
- Comments of Ruby L. Holborn
- Comments of Ruby L. Holborn Confidential (not available to the public)
- Comments of James and Julie Kaufman
- Comments of James and Julie Kaufman Confidential (not available to the public)
- Comments of Erik Johnson
- Comments of Jeff Haverly, S.D. Governor's Office of Economic Development
- Comments of Julie Freier
- Comments of Julie Freier Confidential (not available to the public)
- Comments of Ronnie Hornstra
- Comments of Ronnie Hornstra Confidential (not available to the public)
- Comments of Amber Christenson
- Comments of Amber Christenson Confidential (not available to the public)
- Comments of Kelly Pazour
- Comments of Kelly Pazour Confidential (not available to the public)
- Comments of Dave Adam
- Comments of Katie Bartunek
- Comments of Gregg Hubner
- Comments of Marsha Hubner
- Comments of Marsha Hubner Confidential (not available to the public)
- Comments of Darci Adam
- Comments of Darci Adam Confidential (not available to the public)
- Comments of Kristi Mogen
- Contact Pat Beck, Court Reporter to order a written transcript
A hearing will be held by the Commission beginning at 9:00 a.m., CDT, Tuesday, October 9, 2018, through Friday, October 12, 2018, with the marking of exhibits to begin at 8:30 a.m., CDT, on October 9, 2018, in Room 413 of the Capitol Building, 500 E. Capitol Ave., Pierre, South Dakota.
- 09/11/18 - Order For and Notice of Evidentiary Hearing
- Sign In Sheets
- Recordings
- October 9, 2018
- October 10, 2018
- October 11, 2018
- October 12, 2018
- Exhibits for Evidentiary Hearing
- Contact Precision Reporting to order written transcripts.
- 06/01/18 - Notice of Application; Order for and Notice of Public Input Hearing; Notice of Opportunity to Apply for Party Status
06/20/18 - Order Assessing Filing Fee; Authorizing Executive Director to Enter Into a Consulting ContractAn amended order that corrected typographical errors in the original order was issued on 06/29/18.- 06/29/18 - Amended Order Assessing Filing Fee; Authorizing Executive Director to Enter Into a Consulting Contract
- 08/09/18 - Order Granting Party Status and Establishing Procedural Schedule (Gregg Hubner, Marsha Hubner, Paul Schoenfelder, Lisa Schoenfelder, Charles Mix County, Sherman Fuerniss, and Karen Jenkins)
- 09/11/18 - Order For and Notice of Evidentiary Hearing
- 09/14/18 - Order For and Notice of Ad Hoc Motions Hearing
- 09/21/18 - Order Granting Late Party Status (Kelli Pazour)
- 10/01/18 - Order Granting Motion for Telephonic Testimony and Order Denying Motion to Exclude Lay Testimonies and Quashing Subpoenas
- 11/01/18 - Order Redacting Exhibits and Testimonies
- 11/07/18 - Order For and Notice of Ad Hoc Hearing and Decision Date on Less Than 10 Days' Notice
- 11/28/18 - Final Decision and Order Granting Permit to Construct Facilities and Notice of Entry with Attached Permit Conditions
- 02/22/19 - Order Approving Escrow Agreement and Public Liaison Officer
- 05/15/19 - Order Granting Settlement of Permit Violation
- 05/05/20 - Order Granting Extension of Timeline Due to Covid-19
- 07/09/20 - Order Confirming Requirements of Permit Condition 42
Filed Documents:
- 05/30/18 - Prevailing Wind Park, LLC's Letter regarding Application
- Application
- Appendix A - Figures
- Appendix B - Grasslands Analysis
- Appendix C - Wetland Desktop Determination
- Appendix D - Tiers 1 And 2 Wildlife Report
- Appendix E - Raptor Nest Survey Report
- Appendix F - Avian Use Surveys - Year One
- Appendix G - Avian Use Surveys - Year Two
- Appendix H - Bald Eagle Nest Monitoring
- Appendix I - Northern Long-Eared Bat Acoustic Survey
- Appendix J - Northern Long-Eared Bat Presence/Absence Survey
- Appendix K - Whooping Crane Habitat Review
- Appendix L - Bird And Bat Conservation Strategy
- Appendix M - Sound Study
- Appendix N - Shadow Flicker Analysis
- Appendix O - RF Impact Report
- Appendix P - 2009 Berkeley Property Values Study
- Appendix Q - 2013 Berkeley Property Values Study
- Appendix R - Cultural Resources Literature Search Confidential (not available to the public)
- Appendix S - Cultural Resources Desktop Review and
Construction Grid
- Appendix T - Agency Correspondence
- Pre-Filed Direct Testimony of James Damon
- Pre-Filed Direct Testimony of Bridget Canty
- Pre-Filed Direct Testimony of Keith Thorstad
- Pre-Filed Direct Testimony of Aaron Anderson
- Pre-Filed Direct Testimony of Chris Howell
- Application
06/04/18 - PUC Staff's Letter to SD Newspaper Association regarding Notice of Public Hearing- 06/05/18 - PUC Staff's Corrected Letter to SD Newspaper Association regarding Notice of Public Hearing
- 06/19/18 - Land Ownership Map Confidential (not available to the public)
- 06/21/18 - Prevailing Wind Park, LLC's Application to Bon Homme, Charles Mix and Hutchison County Auditors Certificate of Service
- 06/21/18 - Prevailing Wind Park, LLC's Proof of Mailing
- Attachment A - Letter to Landowners with Attachments
- Attachment B - List of Landowners Confidential (not available to the public)
- 07/19/18 - Prevailing Wind Park, LLC's Affidavits of Publication (Tripp Star Ledger, Yankton Daily Press & Dakotan, Scotland Journal, Avon Clarion and The Wagner Post)
- 07/20/18 - Staff's Letter regarding Motion for Adoption of Procedural Schedule
- 07/20/18 - PUC Staff's First Set of Data Requests to Applicant Certificate of Service
- 08/02/18 - Prevailing Wind Park, LLC's Response to the Motion for Adoption of Procedural Schedule
- 08/08/18 - PUC's Affidavits of Publication
- The Wagner Post's Affidavit of Publication (June 20, 2018 and July 11, 2018)
- Yankton Daily Press & Dakotan's Publication (June 20, 2018 and July 11, 2018)
- Avon Clarion's Affidavit of Publication (June 20, 2018)
- Avon Clarion's Affidavit of Publication (July 11, 2018)
- The Tripp Star Ledger's Affidavit of Publication (June 20, 2018)
- The Tripp Star Ledger's Affidavit of Publication (July 11, 2018)
- 08/08/18 - PUC Staff's First Set of Data Requests to Charles Mix County Certificate of Service
- 08/08/18 - PUC Staff's First Set of Data Requests to Intervenors Certificate of Service
- 08/10/18 - Prevailing Wind Park, LLC's Supplemental Testimonies and Exhibits
- 08/16/18 - PUC Staff's Second Set of Data Requests to Applicant Certificate of Service
- 08/17/18 - Notice of Appearance (Reece M. Almond)
- 08/23/18 - PUC Staff's Third Set of Data Requests to Applicant Certificate of Service
- 09/10/18 - PUC Staff's Direct Testimonies and Exhibits
- 09/10/18 - Intervenors' Disclosure of Lay Witnesses (Gregg C. Hubner, Marsha Hubner, Paul M. Schoenfelder and Lisa A. Schoenfelder)
- 09/10/18 - Intervenors' Direct Testimonies and Exhibits
- 09/11/18 - Karen D. Jenkins' Letter regarding Testimony
- 09/13/18 - Intervenors' Motion To Have Witnesses Appear Telephonically and Certificate of Service
- 09/14/18 - Prevailing Wind Park, LLC's Letter regarding Answer to the Application for Party Status of Kelli Pazour
- 09/14/18 - Prevailing Wind Park, LLC's Letter regarding Motion to Exclude Lay Testimony, to Quash Subpoenas and to Require Further Disclosures
- 09/14/18 - Staff's Response to Late Intervention
- 09/19/18 - Staff's Response to Applicant's Motion to Exclude Lay Testimony, to Quash Subpoenas and to Require Further Disclosures
- 09/19/18 - PUC Staff's Second Set of Data Requests to Intervenors Mr. Reece M. Almond - Representing: Gregg C. Hubner, Marsha Hubner, Paul M.
Schoenfelder and Lisa A. SchoenfelderCertificate of Service - 09/19/18 - Prevailing Wind Park, LLC's Letter regarding Applicant’s Response to Intervenors’ Motion to Have Witnesses Appear Telephonically
- 09/19/18 - Intervenors' Response to Applicant's Motion to Exclude Lay Testimony, to Quash Subpoenas and to Require Further Lay Disclosures (Reese Almond - Representing: Gregg C. Hubner, Marsha Hubner, Paul M. Schoenfelder and Lisa A. Schoenfelder )
- 09/20/18 - PUC Staff's Fourth and Fifth Set of Data Requests to Applicant Certificate of Service
- 09/20/18 - Intervenor Response to Applicant's Motion to Exclude Lay Testimony, to Quash Subpoenas, and to Require Further Lay Disclosures (Karen Jenkins)
- 09/26/18 - Intervenor's Subpoena for Testimony at Evidentiary Hearing to Michael Soukup (Reese Almond - Representing: Gregg C. Hubner, Marsha Hubner, Paul M. Schoenfelder and Lisa A. Schoenfelder) and Certificate of Service
- 09/26/18 - Intervenor's Subpoena for Testimony at Evidentiary Hearing to Keith Mushitz (Reese Almond - Representing: Gregg C. Hubner, Marsha Hubner, Paul M. Schoenfelder and Lisa A. Schoenfelder) and Certificate of Service
- 09/26/18 - Response of Sherman Fuerniss to Direct Testimonies
- 09/26/18 - Applicant's Rebuttal Testimonies and Exhibits and Applicant's Lay Witness Disclosures
- 09/28/18 - PUC Staff's Sixth Set of Data Requests to Applicant Certificate of Service
- 09/28/18 - PUC Staff's Second Set of Data Requests to Intervenor Sherman Fuerniss Certificate of Service
- 10/01/18 - Intervenor's Subpoena for Testimony at Evidentiary Hearing to Jack Soulek (Reese Almond - Representing: Gregg C. Hubner, Marsha Hubner, Paul M. Schoenfelder and Lisa A. Schoenfelder) and Certificate of Service
- 10/01/18 - Staff's Witness List and Exhibit List & Exhibits
- 10/01/18 - Intervenor' Exhibits (Sherman Fuerniss)
- 10/01/18 - Applicant's Witness List & Exhibit List & Exhibits
- 10/01/18 - Intervenors' Witness List and Exhibit List (Reece M. Almond, Davenport, Evans, Hurwitz & Smith LLP - Representing: Gregg C. Hubner, Marsha Hubner, Paul M. Schoenfelder and Lisa A. Schoenfelder)
- 10/02/18 - Intervenors' Exhibits (Reece M. Almond, Davenport, Evans, Hurwitz & Smith LLP - Representing: Gregg C. Hubner, Marsha Hubner, Paul M. Schoenfelder and Lisa A. Schoenfelder)
- 10/02/18 - Intervenors' Exhibits (Karen Jenkins)
- 10/04/18 - Applicant's Corrected Exhibit A5
- 10/04/18 - Intervenor's Subpoena for Testimony at Evidentiary Hearing to Eric Elsberry (Reese Almond - Representing: Gregg C. Hubner, Marsha Hubner, Paul M. Schoenfelder and Lisa A. Schoenfelder) and Certificate of Service
- 10/04/18 - Eric Elsberry's Admission of Service of Subpoena
- 10/04/18 - Charles Mix County Sheriff Office's Return of Service for Keith Mushitz
- 10/04/18 - Michael Soukup's Admission of Service of Subpoena
- 10/04/18 - Intervenors' Additional Exhibits (Karen Jenkins)
- 10/05/18 - Intervenors' Corrected Exhibit I-16 and Additional Exhibit I-17 (Reece M. Almond, Davenport, Evans, Hurwitz & Smith LLP - Representing: Gregg C. Hubner, Marsha Hubner, Paul M. Schoenfelder and Lisa A. Schoenfelder)
- 10/05/18 - Intervenors' Additional Exhibits (Sherman Fuerniss)
- 10/05/18 - PUC Staff's Response to Intervenors' First Data Request Certificate of Service
- 10/09/18 - Intervenors' Opposition to Having Exhibits I-16 and I-17 be Confidential and Certificate of Service
- 10/09/18 - Intervenors' Exhibits I-16, I-17, I-28, I-29 and I-30 (Reece M. Almond, Davenport, Evans, Hurwitz & Smith LLP - Representing: Gregg C. Hubner, Marsha Hubner, Paul M. Schoenfelder and Lisa A. Schoenfelder)
- 10/09/18 - Applicant's Exhibits A3-2; A10-2; A-16R; A20-1; A20-2; A22-2; A22-3; A24; A25; A27; A28; A29; A30; A31; A32; A33
- 10/09/18 - Staff's Exhibit S5
- 10/29/18 - Prevailing Wind Park, LLC's Letter regarding Exhibit A42
- 10/29/18 - Hearing Examiner's Redacted Exhibits I-1 and I-2, and Evidentiary Hearing Transcript for October 11, 2018
- 11/13/18 - Sherman Fuerniss' Post-Hearing Brief
- 11/13/18 - Intervenors' Post-Hearing Brief and Certificate of Service (Reece M. Almond, Davenport, Evans, Hurwitz & Smith LLP - Representing: Gregg C. Hubner, Marsha Hubner, Paul M. Schoenfelder and Lisa A. Schoenfelder)
- 11/13/18 - PUC Staff's Letter regarding Post-Hearing Brief
- Staff's Post-Hearing Brief
- Staff's Post-Hearing Brief Confidential (not available to the public)
- Certificate of Service
- Staff's Post-Hearing Brief
- 11/13/18 - Prevailing Wind Park, LLC's Letter regarding Post-Hearing Brief
- 11/13/18 - Karen Jenkins' Post-Hearing Brief
- 11/14/18 - Kelli Pazour's Post-Hearing Brief
- 11/19/18 - Prevailing Wind Park, LLC's Letter regarding Applicant’s and Staff’s Revised Joint Proposed Condition 29 and New Joint Proposed Condition
- 01/23/19 - Prevailing Wind Park, LLC's Letter regarding Applicant’s Proposed Public Liaison Officer – Condition 36
- 01/28/19 - WAPA's Letter regarding Draft EA
- 02/07/19 - Prevailing Wind Park, LLC's Letter regarding Proposed Escrow Agreement
- 03/21/19 - Prevailing Wind Park, LLC's Letter regarding Condition No. 36
- 03/21/19 - Prevailing Wind Park, LLC's Letter regarding Condition No. 36
- Proof of Mailing
- Exhibit A - Public Liaison Officer Notification Letter
- Exhibit B - Landowner Notice for Start of Construction
- Exhibit B-1 - Final Decision and Order Granting Permit to Construct Facilities and Notice of Entry
- Exhibit B-2 - Prevailing Wind Park, LLC Construction/Maintenance Damage Compensation Plans and Procedures Confidential (not available to the public)
- Exhibit B-3 - Detailed Safety Information
- Exhibit C - Landowner Mailing List Confidential (not available to the public)
- Certificate of Service
- Proof of Mailing
- 03/29/19 - Prevailing Wind Park, LLC's Letter regarding Conditions No. 14, 15, 23 and 29
- Architectural Resources Survey (Condition 14) Confidential (not available to the public)
- Level III Intensive Archaeological Survey (Condition 14) Confidential (not available to the public)
- Stormwater Pollution Prevention Plan (“SWPPP”) (Condition 15)
- Affidavit of Randy Corey Providing Notice of Turbine Adjustments Up to
250 Feet (Condition 23) - Exhibit A - Maps of Turbine Adjustments (Condition 23)
- Exhibit B - Summary of Turbine Adjustment Requirement Compliance (Condition 23)
- Exhibit C - Updated sound level analysis (Conditions 23 and 29(b))
- Exhibit D - Updated shadow flicker analysis (Conditions 23 and 29(c))
- Figure showing the most current preconstruction design, layout, and plans (Condition 29(a))
- Affidavit of Randy Corey Identifying the Turbines that will be Operationally Controlled
- Certificate of Service
- 04/23/19 - Prevailing Wind Park, LLC's Letter regarding Condition No. 40
- Escrow Agreement with Exhibits Confidential (not available to the public)
- Certificate of Service
- 04/25/19 - Prevailing Wind Park, LLC's Letter regarding Condition No. 29 with Photos
- 04/29/19 - Prevailing Wind Park, LLC's Corrected Letter regarding Condition No. 29
- 04/29/19 - Sherman Fuerniss' Comments on Prevailing Wind Park, LLC's Letters Dated April 25, 2019 and April 29, 2019
- 04/29/19 - Prevailing Wind Park, LLC's Letter regarding Condition No. 1
- United States Fish and Wildlife Service Finding of No Significant Impact for the
Prevailing Wind Park Energy Facility Project - South Dakota Department of Environment and Natural Resources Grant of
Coverage to Prevailing Wind Park under General Permit Authorizing Stormwater
Discharges Associated with Construction Activities, Permit No. SDR10J380 - Bon Homme County, Large Wind Energy System Permit Approval (Bon Homme County Commission Meeting Minutes, August 21, 2018)
- Bon Homme County, Building Permits Nos. BP 2019-007 through BP 2019-039
(Turbines) - Bon Homme County, Building Permit No. BP 2019-040 (O&M/Substation)
- Bon Homme County, Utility Permit
- Charles Mix County, Building Permits Nos. 2477 through 2499 (Turbines) With
Approval of Extensions - Charles Mix County, Building Permit No. 2598 (Meteorological Tower)
- Charles Mix County, Utility Permit
- Hutchinson County, Utility Permit
- Certificate of Service
- United States Fish and Wildlife Service Finding of No Significant Impact for the
- 05/14/19 - Prevailing Wind Park, LLC's Letter regarding Construction Figure
- 05/14/19 - Sherman Fuerniss' Handout at the May 14, 2019, Commission Meeting
- 05/16/19 - Docket Closed
- 05/16/19 - Intervenors Gregg C. Hubner, Marsha Hubner, Paul M. Schoenfelder and Lisa A. Schoenfelder's Letter regarding Supplemental Comments of Richard R. James
- 05/29/19 - Prevailing Wind Park, LLC's Letter and Civil Penalty Payment
- 06/20/19 - Prevailing Wind Park, LLC's Letter regarding Project Design Overview for Prevailing Wind Park as of March 29, 2019
- 07/08/19 - Prevailing Wind Park, LLC's Letter regarding Condition No. 23
- Affidavit of Peter Pawlowski Providing Notice of Turbine Adjustment Up to 250 Feet
- Exhibit A - Map of Turbine Adjustment (Turbine 40)
- Exhibit B - Summary of Turbine Adjustment Requirement Compliance (Turbine 40)
- Exhibit C - Updated Sound Level Analysis Results
- Exhibit D - Updated Shadow Flicker Analysis Results
- Level III Intensive Archaeological Survey Addendum Report (Turbine 42) Confidential (not available to the public)
- Turbine 42 Constraints Map
- Updated Project Layout Constraints Maps
- Certificate of Service
- Affidavit of Peter Pawlowski Providing Notice of Turbine Adjustment Up to 250 Feet
- 07/18/19 - Prevailing Wind Park, LLC's Letter regarding Condition No. 23 Confidential (not available to the public)
- Affidavit of Peter Pawlowski Providing Notice of Turbine Adjustment Up To 250 Feet Confidential (not available to the public)
- Exhibit A - Map of Turbine Adjustment and Updated Project Constraints Map Confidential (not available to the public)
- Exhibit B - Summary of Turbine Adjustment Requirement Compliance Confidential (not available to the public)
- Exhibit C - Updated Sound Level Analysis Results Confidential (not available to the public)
- Exhibit D - Updated Shadow Flicker Analysis Results Confidential (not available to the public)
- Certificate of Service
- Affidavit of Peter Pawlowski Providing Notice of Turbine Adjustment Up To 250 Feet Confidential (not available to the public)
- 07/25/19 - Prevailing Wind Park, LLC's Letter regarding Condition No. 23
- 07/29/19 - Prevailing Wind Park, LLC's Letter regarding Withdawal of Turbine Shifts
- 08/06/19 - Prevailing Wind Park, LLC's Letter regarding Condition 23 (Turbine No. 8)
- 09/03/19 - PUC Staff's Letter regarding Prevailing Wind Park Turbine 8 Material Deviation
- 04/03/20 - Intervenor Gregg Hubner’s Letter to the Commission
- 04/06/20 - Intervenor Gregg Hubner's Response to Chairman Hanson's Response
- 04/20/20 - Intervenor Gregg Hubner's Email to Chairman Hanson
- 04/21/20 - Commission Staff's Response to Gregg Hubner
- 04/21/20 - Prevailing Wind Park, LLC's Letter regarding Condition 41 Request for Exemption for Condition 42 due to COVID-19
- 04/23/20 - Prevailing Wind Park, LLC's Letter regarding the Status of Project Construction
- 05/14/20 - Intervenor Gregg Hubner's Email to the Commission
- 05/26/20 - Prevailing Wind Park, LLC's Letter regarding Condition 1
- Federal Aviation Administration Determinations of No Hazard
- FAA Marking & Lighting Recommendations
- U.S. Army Corps of Engineers Clean Water Act Section 404 Coverage
- S.D. Department of Transportation Utility Permits
- S.D. DOT Highway Access Permits
- S.D. Electrical Commission Electrical Inspection/Permits
- Bon Homme County Condition Use Permit No. BP 2019043CU (ADLS tower)
- Bon Homme County Building Permit No. BP 2019-081 (permanent meteorological tower) - Replacement filed 05/27/20
- Bon Homme County Road Approach Permits
- Bon Homme County Utility Permit
- Charles Mix County Utility Permit
- Charles Mix County Approach Permit
- Hutchinson County Conditions Use Permits and 509 Approvals
- Hutchinson County Ingress/Egress Permits
- Hutchinson County Building Permits
- Certificate of Service
- 05/27/20 - Prevailing Wind Park, LLC's Letter regarding Condition 1
- 06/29/20 - Prevailing Wind Park, LLC's Letter regarding Condition 42
- 07/21/20 - Prevailing Wind Park, LLC's Letter regarding Condition 30
- 08/31/20 - Prevailing Wind Park, LLC's Letter regarding Condition 42
- 10/01/20 - PUC Staff’s Letter regarding Condition 42
- 11/17/20 - Intervenor Gregg Hubner's Email to PUC
- 01/04/21 - Intervenor Gregg Hubner's Email to PUC
- 01/21/21 - Prevailing Wind Park, LLC's Letter regarding Condition 28
- 01/22/21 - Prevailing Wind Park, LLC's Letter regarding Condition 32
- 04/12/21 - Prevailing Wind Park, LLC's Letter regarding Condition 9(e)
- 06/01/21 - Prevailing Wind Park, LLC's Letter regarding Escrow Statements of Account
- 05/17/22 - Prevailing Wind Park, LLC's Letter regarding Condition 34
- Post-Construction Bird and Bat Fatality Monitoring Study - March 2020 - March 2021 Confidential (not available to the public)
- Certificate of Service
- 11/09/23 - Docket Reclosed