South Dakota Public Utilities Commission Meeting
March 17, 2015, at 9:30 A.M. CDT
Room 413, Capitol Building
Pierre, South Dakota
NOTE: If you wish to join this meeting by conference call, please contact the Commission at 605-773-3201 by 5:00 p.m. CDT on Monday, March 16, 2015. Lines are limited and are given out on a first come, first served basis, subject to possible reassignment to accommodate persons who must appear in a proceeding. Ultimately, if you wish to participate in the Commission Meeting and a line is not available, you may have to appear in person.
NOTE: To listen to the Commission Meeting live please go to the PUC's website www.puc.sd.gov and click on the LIVE link on the home page. The Commission requests persons who will only be listening to proceedings and not actively appearing in a case listen via the web cast to free phone lines for those who have to appear. The Commission meetings are archived on the PUC's website under the Commission Actions tab, Click on “Commission Meeting Archives,” to access the recordings.
NOTE: Notice is further given to persons with disabilities that this Commission meeting is being held in a physically accessible place. If you have special needs, please notify the Commission and we will make all necessary arrangements.
AGENDA OF COMMISSION MEETING
Administration
1. Approval of the Minutes of the Commission Meeting Held on March 2, 2015 (Staff: Joy Lashley)
Consumer Reports
1. Status Report on Consumer Utility Inquiries and Complaints Received by the Commission (Consumer Affairs: Deb Gregg)
Electric
On February 25, 2014, Black Hills Power, Inc. (BHP) filed its 2014 Economic Development Plan which includes 2013 actual expenses and the 2014 proposed budget. On March 4, 2015, BHP filed a letter requesting to withdraw this docket as it was determined that economic development cost recovery should be granted through a general rate case prior to filing an economic development plan.
TODAY, shall the Commission grant Black Hills Power, Inc.'s request for withdrawal?
On December 23, 2014, Black Hills Power, Inc. (BHP) filed for approval of its vegetation management activities from April 2013 through November 2014, the 2015 vegetation management budget, and the Vegetation Management Regulatory Asset (VMRA) balance as of November 30, 2014. Per the Settlement Stipulation in EL12-061, this filing includes a report which outlines the progress made on the overall five-year plan and updates the forecast for the remaining years based on actual progress to date.
TODAY, shall the Commission approve the April 2013 through November 2014 vegetation management activities, the 2015 vegetation management budget, and the November 30, 2014, VMRA balance?
On January 14, 2015, Commission Staff filed an Electric Service Territory Boundary Agreement between Parker Public Utilities and Southeastern Electric Cooperative, Inc. This filing is made pursuant to current efforts of the PUC to verify electric territory mapping data for conversion to electronic format and use in a Geographic Information System (GIS) database. With the assistance of the above-referenced utilities, Commission Staff has confirmed the service territory boundary shared by these utilities and has prepared updated mapping information. Commission Staff asks for approval of the agreement to update official mapping data to properly reflect the service territory boundaries shared by the utilities in this docket.
TODAY, shall the Commission approve the proposed electric service territory boundary agreement?
Items for Commission Discussion
Announcements
- The PUC will have an exhibit booth at the Black Hills Home Builders Association Home Show, March 27-29, 2015, at the Rushmore Plaza Civic Center, Rapid City, S.D.
- The next regularly scheduled commission meeting will be Tuesday, March 31, 2015, at 9:30 a.m. CST in Room 413 at the State Capitol Building, Pierre, S.D.
- Commission meetings are scheduled for April 14 and 30, 2015.
/s/Cindy Kemnitz
Cindy Kemnitz
Finance Manager
PUC Email