Consumer Assistance | Energy | Telecom | Warehouse | Commission Actions | Miscellaneous
arrow Commission Agendas | previous page

South Dakota Public Utilities Commission Meeting
June 15, 2010, at 9:30 A.M. CDT
Room 413, Capitol Building
Pierre, South Dakota

NOTE:  If you wish to join this meeting by conference call, please contact the Commission at 605-773-3201 by 5:00 p.m. CDT on June 14, 2010.  Lines are limited and are given out on a first come, first served basis, subject to possible reassignment to accommodate persons who must appear in a proceeding. Ultimately, if you wish to participate in the Commission Meeting and a line is not available you may have to appear in person.  

NOTE:  To listen to the Commission Meeting live please go to the PUC's Web site www.puc.sd.gov and click on the LIVE link on the home page. The Commission requests that persons who will only be listening to proceedings and not actively appearing in a case listen via the web cast to free phone lines for those who have to appear.  The Commission meetings are archived on the PUC's Web site under the Commission Actions tab and then click on the LISTEN link on the page.

NOTE:  Notice is further given to persons with disabilities that this Commission meeting is being held in a physically accessible place. If you have special needs, please notify the Commission and we will make all necessary arrangements.

ADDENDUM TO THE
AGENDA OF COMMISSION MEETING

Natural Gas

1.      NG10-003       In the Matter of the Filing by NorthWestern Corporation dba NorthWestern Energy for Approval of a Contract with Deviations. (Staff Analyst: Dave Jacobson, Staff Attorney: Karen Cremer)

         On June 9, 2010, the Commission received an application by NorthWestern Corporation dba NorthWestern Energy (NorthWestern) for approval of a contract with deviation to construct a natural gas line to serve the South Dakota Wheat Growers Aberdeen East Facility. NorthWestern will install, or arrange for the installation of, approximately 1/2 mile of 4-inch pipeline. The deviated rate will allow NorthWestern to fully recover the cost of the upgrade, after which the customer will revert back to Rate 86 tariffed rates.

         TODAY, Shall the Commission approve the Contract with Deviation and Associated Tariff Revision with an effective date of June 15, 2010?

2.      NG10-004       In the Matter of the Filing by NorthWestern Corporation dba NorthWestern Energy for Approval of a Contract with Deviations. (Staff Analyst: Dave Jacobson, Staff Attorney: Karen Cremer)

         On June 9, 2010, the Commission received an application by NorthWestern Corporation dba NorthWestern Energy (NorthWestern) for approval of a contract with deviation to construct a natural gas line to serve the South Dakota Wheat Growers Facility in Willow Lake, South Dakota. NorthWestern will upgrade, or arrange for the upgrade, to a 4-inch pipeline. The deviated rate will allow NorthWestern to fully recover the cost of the upgrade, after which the customer will revert back to Rate 86 tariffed rates.  

      TODAY, Shall the Commission approve the Contract with Deviation and Associated Tariff Revision with an effective date of June 15, 2010?

3.      NG10-005       In the Matter of the Filing by NorthWestern Corporation dba NorthWestern Energy for Approval of a Contract with Deviations. (Staff Analyst: Dave Jacobson, Staff Attorney: Karen Cremer)

         On June 9, 2010, the Commission received an application by NorthWestern Corporation dba NorthWestern Energy (NorthWestern) for approval of a contract with deviation to construct a natural gas line to serve the South Dakota Wheat Growers facility in Andover, South Dakota. NorthWestern will install, or arrange for the installation of, approximately five miles of 4-inch pipeline to serve a new grain drying facility. The deviated rate will allow NorthWestern to fully recover the cost of the upgrade, after which the customer will revert back to Rate 86 tariffed rates. 

      TODAY, Shall the Commission approve the Contract with Deviation and Associated Tariff Revision with an effective date of June 15, 2010?

4.      NG10-006       In the Matter of the Filing by NorthWestern Corporation dba NorthWestern Energy for Approval of a Contract with Deviations. (Staff Analyst: Dave Jacobson, Staff Attorney: Karen Cremer)

           On June 9, 2010, the Commission received an application by NorthWestern Corporation dba NorthWestern Energy (NorthWestern) for approval of a contract with deviation to upgrade a natural gas line to serve the South Dakota Wheat Growers expanded grain drying facility in Yale, South Dakota. NorthWestern will upgrade, or arrange for the upgrade, to a 4-inch pipeline. The deviated rate will allow NorthWestern to fully recover the cost of the upgrade, after which the customer will revert back to Rate 86 tariffed rates.  

         TODAY, Shall the Commission approve the Contract with Deviation and Associated Tariff Revision with an effective date of June 15, 2010?

/S/Cindy Kemnitz                                     .
Cindy Kemnitz
Finance Manager
puc@state.sd.us